Grouted – Wall Panel

Grouted – Wall Panel

Grouted base connections are a cost effective choice when design criteria will allow for their use. Grout tubes are filled with non-shrink grout (up to 10,000 psi required) prior to panel erection. Dowels protruding from precast are set into wet grout and panel is set at the correct elevation on shims.  Grouting under the base of the panel is completed after precast connections have been completed.

NMB – Wall Panel

NMB – Wall Panel

NMB splice sleeves can be used in a variety of precast products that require a type 2 coupler. Rebar is constructed protruding from foundation and then cut to a specific distance above the foundation as required by size of NMB splice sleeve.  Female slice sleeve is embedded in precast and placed over protruding foundation rebar.  Once connection is complete at desired elevation, high strength mortar (that is provided solely by NMB manufacturer) is ejected into the sleeve via grouting tubes to complete connection.

V-Pocket – Wall Panel

V-Pocket – Wall Panel

V-Pocket base connections are typically used when design connection performance does not allow for a grout tube connection.  V-pocket connection require a CIP embed to be installed in the foundation prior to precast installation.  Once panel is shimmed to correct elevation, steel tabs are welded between CIP embed and V-shaped precast embed to complete connection.  Access needs to be considered when using connection near columns or other site obstructions.

NMB – Column

NMB – Column

NMB splice sleeves can be used in a variety of precast products that require a type 2 coupler. Rebar is constructed protruding from foundation and then cut to a specific distance above the foundation as required by size of NMB splice sleeve.  Female slice sleeve is embedded in precast and placed over protruding foundation rebar.  Once connection is complete at desired elevation, high strength mortar (that is provided solely by NMB manufacturer) is ejected into the sleeve via grouting tubes to complete connection.

Intermediate CIP Slab

Intermediate CIP Slab

When  required, intermediate conditions often include a connection from precast to CIP slab.  In this scenario, CIP embed design and location are coordinated and CIP embeds are installed onsite prior to precast installation per plan.  A combination of slotted angle welded to the CIP embed and directional inserts embedded in precast allow for required movement.

Roof Perimeter Beam

Roof Perimeter Beam

Often perimeter roof connections are completed to top of beam, bottom of beam or extending bent plate.  Design coordination between the provider of bent plate critical as bent plate is commonly supplied by steel manufacture prior to completion of connection design.  A combination of slotted angle welded to steel and directional inserts embedded in precast allow for required movement.

Wall Panel – DT

Wall Panel – DT

Pocket assemblies designed to hide connections can be used between Double Tee and Wall Panel assemblies.  Double Tee stem spacing = 6′-0″ and Maximum Double Tee width = 12′-0″.  Supporting wall panel layout is key and often is similar to Double Tee flange width to allow stems (and concentrated loads) to be centered in panel.

Grouted – Wall Panel

Grouted base connections are a cost effective choice when design criteria will allow for their use. Grout tubes are filled with non-shrink grout (up to 10,000 psi required) prior to panel erection. Dowels protruding from precast are set into wet grout and panel is set at the correct elevation on shims.  Grouting under the base of the panel is completed after precast connections have been completed.

NMB – Wall Panel

NMB splice sleeves can be used in a variety of precast products that require a type 2 coupler. Rebar is constructed protruding from foundation and then cut to a specific distance above the foundation as required by size of NMB splice sleeve.  Female slice sleeve is embedded in precast and placed over protruding foundation rebar.  Once connection is complete at desired elevation, high strength mortar (that is provided solely by NMB manufacturer) is ejected into the sleeve via grouting tubes to complete connection.

V-Pocket – Wall Panel

V-Pocket base connections are typically used when design connection performance does not allow for a grout tube connection.  V-pocket connection require a CIP embed to be installed in the foundation prior to precast installation.  Once panel is shimmed to correct elevation, steel tabs are welded between CIP embed and V-shaped precast embed to complete connection.  Access needs to be considered when using connection near columns or other site obstructions.

NMB – Column

NMB splice sleeves can be used in a variety of precast products that require a type 2 coupler. Rebar is constructed protruding from foundation and then cut to a specific distance above the foundation as required by size of NMB splice sleeve.  Female slice sleeve is embedded in precast and placed over protruding foundation rebar.  Once connection is complete at desired elevation, high strength mortar (that is provided solely by NMB manufacturer) is ejected into the sleeve via grouting tubes to complete connection.

Intermediate CIP Slab

When  required, intermediate conditions often include a connection from precast to CIP slab.  In this scenario, CIP embed design and location are coordinated and CIP embeds are installed onsite prior to precast installation per plan.  A combination of slotted angle welded to the CIP embed and directional inserts embedded in precast allow for required movement.

Roof Perimeter Beam

Often perimeter roof connections are completed to top of beam, bottom of beam or extending bent plate.  Design coordination between the provider of bent plate critical as bent plate is commonly supplied by steel manufacture prior to completion of connection design.  A combination of slotted angle welded to steel and directional inserts embedded in precast allow for required movement.

Wall Panel – DT

Pocket assemblies designed to hide connections can be used between Double Tee and Wall Panel assemblies.  Double Tee stem spacing = 6′-0″ and Maximum Double Tee width = 12′-0″.  Supporting wall panel layout is key and often is similar to Double Tee flange width to allow stems (and concentrated loads) to be centered in panel.

image
image

Data Center Design

 

Accelerated Schedules

Data centers have condensed schedules and overall construction durations. Design/fabrication of precast can begin while foundations are being constructed and scheduled to arrive on-site, ready for installation.

Energy Efficient

Precast panels meet ASHRAE 90.1 energy standards for buildings and can deliver R-values up to 30 depending on the thickness of the foam.

Dry & mold free
Precast panels do not have interior voids where air and water can collect, which are common to other framing systems. These voids can support mold growth, which is especially detrimental in sensitive data center environments.

Finish

Data centers typically require higher-end exterior finishes. Insulated precast panels can include high-end architectural mix designs and finishes on the exterior wythe only, reducing the total quantity and cost.

Quality Construction

Precast panels are fabricated in a controlled environment to the highest industry standards. That is extremely critical for exterior and interior exposed finishes that may require a higher level of finish that can only be fabricated in a controlled environment.

3D Viewer

3D Viewer Tools and Functions:

  • 3D Viewer Functions:
  • Move, span, zoom assemblies
  • Isolate single components in view
  • Explode assembly single components
  • Use markup to sketch details
  • General measurements for concept
  • Print views

See Related Product Pages Below

Other Industrial Projects

View All Projects